Saturday, July 4, 2009

PART TWO: NOW YOU SEE IT, SOON YOU WON'T!!


In the last posting, you saw photographs of the plumbing which had been placed in the wing where the bathrooms are to be located. The photograph above (left) shows the same area after gravel has been placed in preparation for pouring the concrete floor. In the last article, the HVAC duct work was exposed. Now, (right photo), the ducts have been encased with concrete. The next step is for gravel to be placed (this should happen the week of July 6th) in preparation for the concrete floor to be poured in the Day Chapel.

The above photographs show the progress that has been made on the roof/ceiling. As you saw last time, the plating (wood) had been placed on the steel girders. Now you can see the ceiling has been installed in much of the Nave (right). The photograph on the left shows the outside, which has plywood over the ceiling and tar paper. After completing this process over the entire Nave and Day Chapel, it will be time for the roofing to be installed.

In the last posting, all you could see were the metal frames around the front of the church. Now that framing has been covered. There are two different boards placed around the church. The plywood is where stone will be installed and the other boards will be where brick will be laid. If all goes well, this process will begin the week of July 6th also.











Saturday, June 20, 2009

NOW YOU SEE IT, SOON YOU WON'T!!

Even though the monsoons have left us, we still had rain everyday last week. That's the bad news, but the good news is that we had sub contractors working all but one day and one crew came in and worked a full day on Saturday. In fact, I'm not sure that we could have fit any more equipment or personnel on the property than we had. As the title indicates, the work taking place now, will soon be out of sight. I thought this would be a good time to show you close ups of activities taking place.

These photos show the work taking place on the plumbing for the bathrooms. In the next week or so, the concrete floor will will be poured on top of all these pipes.

When we begin holding services, we want to have an efficiently operated HVAC system. This would not be possible without hundreds of feet of underground ductwork. These photos show some of the ductwork that will go from the basement along the side of the main nave. You can also see the amount of piping that is being installed in the Day Chapel. It crosses from side to side. All of this ductwork will soon be encased in concrete.

The activity taking place in the air, is called "plating". This is when wood in bolted to the steel beams. After this work is done, the wood ceiling will be mounted to the beams. The planks for the ceiling will arrive on Monday with installation beginning then.

What is easy to see now, is the shape of the church as the metal studs are being installed along the front entrance. The outside framing will continue next week, along with the framing of the walls inside the Narthex.

Saturday, June 6, 2009

DID SOMEONE SAY NATATORIUM?

Anyone who lives in Greensboro knows we had more than our share of rain since Wednesday night. The monsoons hit us late afternoon with as much as 7 inches of rain flooding homes and roads throughout Greensboro. According to the rain gage, we had 3 inches of rain at the church . Even though the basement is almost totally enclosed, 18 inches of water poured in, which would be a good start toward a Natatorium. The water came down the trenches where the HVAC is being installed and into the openings in the side walls. On Thursday with the pump working all day, the water level in the basement was down to 6 inches, then came more rain that night. Friday morning the level was up to 23 inches and the pump kept running. With the pumps still running, the water was back down to a few inches when I checked midday on Saturday.
Even though, we had that setback, this was a good week. You will notice at Mass this weekend that the steel has all been erected and the church is now taking shape. You can clearly see the shape of the Main Nave, Day Chapel and locations where the stained glass windows will be placed. Even with the weather delays we continue to make progress toward "Making A Place At The Table"

Sunday, May 31, 2009

AN EARLY MORNING DELIVERY

At 5:30 AM on Friday, May 29th, two 9 ton, 70 foot long steel girders made the 5 mile trek up Elm Street from Williams Steel. By 6:10 AM the driver had maneuvered his rig onto our property and the girders were ready to be unloaded.

Msgr. Marcaccio, Parish Commission Chair Dick Pauley, and Building Chair Tom Martin check out the girders after their arrival. Fortunately they didn't have to do anything but watch.
A little after 8:00 the first of the girders was hoisted into the air and by 8:15 it had been bolted into place. The activity was exciting for the school carpool line and gave everyone a lot to look at. Several parish members stopped by to watch the excitement. Joe Plesh and Guy Lizotte pose in front of the newly erected girder. The second large beam is goes up on Monday.

Monday, May 25, 2009

More Steel on the Way!!










Happy Memorial Day! There was no activity on our church today, but that all changes tomorrow. The last 2 weeks have provided us with the framework for the Narthex and Day Chapel as well as the floor and decking for the Narthex. Tomorrow, a larger crane which you may have seen this weekend will be setup and ready for the first truck to arrive with the steel for the Main Nave.








These Photos show the results of the last week. With luck from the weather

Sunday, May 17, 2009

Steeling ourselves


If you've driven past our construction site on North Elm this week, you've seen how our new church is really starting to take shape.

Williams Steel, a Greensboro firm located on South Elm-Eugene Street has been working to fabricate all the steel we'll need for"Making a Place at the Table".


The company loaded up six trucks and started bringing it all 200 pieces of steel over, piece by piece on Monday, May 11th.

As the workers unloaded the steel beams, they laid them out across the site in preparation for construction -- which would start the same day. By Monday afternoon, many of the uprights were already in place.


This week, work has been done in the narthex, the chorus practice room/family room, bathrooms, the side wall opposite Elm Street and the day Cchapel. Currently the basement is 80% completed.

The outline is emerging:

As you look at this view of our church, here are a couple of interesting points. The square you notice at the top of the narthex is where a skylight will flood our sanctuary with natural light. And even though we can see the outline of our church, the central nave in the sanctuary will actually be 17 feet higher than the steel which has already been erected.

This week workers will continue to use the steel onsite so watch for more growth and changes as the narthex and day chapel will be framed in steel. The concrete floor of the narthex will be poured and the crane repositioned for the rest of the steel to come.

Phase II of our steel work is expected to begin May 26th when the next round of steel comes. That work will include the sanctuary. Also in late May or early June, the two largest beams which form the center nave will be delivered. These beams each weigh 9 tons and are 70 feet long. Here's one of them, from a photo taken at Williams Steel.

These two huge beams will most likely come to our site at night and go directly from the truck to their final places in the center nave. We expect all the steel work to be completed in 30 working days.

Special thanks to Tom Martin for his photos, timeline and construction tidbits.

Friday, May 8, 2009

A Construction Tail

When Saint Pius X Church started "Making a Place at the Table" for all in our parish, we never expected to have this unusual family take us up on the offer.

A feral cat who has long visited our church grounds, created her own "Place at the Table" when she delivered five kittens behind an AC unit beside the Kloster Center. When workers lifted that unit this week, they found the three-week old kittens huddled together.
The workers used materials at hand to keep the kittens safe, while calling the church office with the news.


Teresa Marie Vestal and Jeanine Lazusky grabbed a mail carrier box and a towel to collect the kittens: three boys and two girls, all in great health. You can see how cute they are in these photos. All together, there were two calico females, two orange males and one black male with white paws.

Just look at those faces! Teresa and Janine spent about an hour with them, showing them to the Saint Pius X school office staff. That's when first grade assistant Mrs. Holly Fortun called her neighbor, Cynthia Johnson, who quickly came over to bottle feed the new kittens. Not only did she feed them lunch that day, but she also made arrangements to have the kittens receive their first shots, get dewormed and even found a home for one of the orange males.

Monsignor's veterinarian, Dr. Tina, took on the kittens as new patients and cleared them to be placed in homes once they can eat on their own.

Meantime, we're so grateful to Cynthia Johnson for her time and effort to keep our new parish pets healthy until their adoption days come.

One of our parishioners, Peggy Delisi, has tried to catch the feral mom for several years, and owns several kittens from the mama cat's previous litters. The Feral Cat Society has been called, and together we're trying to ensure the mama cat is spayed and then released.

After the kittens' nine lives were spared, construction workers resumed their installation of the new AC units behind the Kloster Center.

Special thanks to Teresa Marie Vestal and Tom Martin for their pictures and accounts of the kittens' tail ... I mean tale.

***
Edited to add update.

If you'd like to adopt one of these kittens when they are old enough, please contact Teresa Marie Vestal. You can email her at teresamarievestal (at) gmail (dot) com.
And I am deliberately spelling out her email address so she is not added to many, many email lists by robot spammers. You would write it in the usual way when you send the email, though.